Dashboard · Meridian Climate Systems

Production

Plan against actual, work finished on time and labour efficiency. By plant, line and month, with the orders to rescue first. Data to 31 October 2026.

Rebuilt with made-up data. The real dashboard is internal.

Period
Plant

Year to date · All plants

2 of 3 figures are off target.

Finished on time and labour efficiency need work. Plant South is furthest behind plan at 90.5%.

  • Vs plan97.0%
  • On time81.1%
  • Efficiency79.4%

Plan vs actual

97.0%

On the 97.0% target

Target 97%103.1 of 106.3 M plan made97%

Finished on time

81.1%

−8.9 pts below the 90.0% target

Target 90%58.7 of 72.3 M finished on time81%

Labour efficiency

79.4%

−0.6 pts below the 80.0% target

Target 80%524k of 660k hours earned79%

Output each month against plan

Output each month against plan, All plants: Jan 9.1 M of 9.3 M, Feb 9.3 M of 9.8 M, Mar 11.2 M of 11.0 M, Apr 10.7 M of 10.8 M, May 11.6 M of 11.3 M, Jun 9.8 M of 10.3 M, Jul 9.5 M of 10.0 M, Aug 9.9 M of 10.5 M, Sep 10.9 M of 11.5 M, Oct 11.2 M of 11.9 M.

Each plant against plan

Tap a plant to filter the page.

Gap to plan by business line

Tap a line to filter the page
Gap to plan by business line, Year to date, All plants: plan 106.3 M, Ducting −0.1 M, Air handling −0.3 M, Fan coils −0.5 M, Packaged units −0.9 M, Chillers −1.3 M.

Open work by stage

30.9 M open today
16%35%12%21%
Open work by stage today, All plants: Planning 4.9 M, Procurement 3.3 M, In production 10.8 M, Quality 3.7 M, Dispatch 6.5 M, Not tracked 1.6 M.

Tap a stage to filter the orders below. Hatched work has no stage recorded yet.

Act first: orders at risk

28 orders, 44.1 M. 23 already late. Largest first.
Production orders at risk, with the reason and the next action
Next action
Westmere LabsMCS-FC-2322 · Fan coilsLate3.24 MPlant SouthIn production8 Oct23 days lateDesign changeRelease the new drawing
Westmere LabsMCS-CH-2939 · ChillersLate3.19 MPlant EastIn production5 Oct26 days lateDesign changeRelease the new drawing
Westmere LabsMCS-AH-2837 · Air handlingLate3.07 MPlant SouthIn production19 Sep42 days lateQuality holdClear the test result
Umber Rail DepotMCS-PU-1828 · Packaged unitsLate3.02 MPlant NorthIn production28 Jul95 days lateDesign changeRelease the new drawing
Tidewater ArenaMCS-PU-2277 · Packaged unitsLate2.90 MPlant EastQuality16 Sep45 days lateMaterial shortExpedite the late part
Quayside OfficesMCS-FC-4046 · Fan coilsLate2.86 MPlant EastDispatch27 Oct4 days lateDesign changeRelease the new drawing
Sablewood ClinicMCS-PU-4270 · Packaged unitsLate2.86 MPlant NorthDispatch17 Aug75 days lateWaiting on test slotBook the test bay
Kestrel Data HallsMCS-FC-3267 · Fan coilsLate2.53 MPlant SouthIn production31 Aug61 days lateCapacityAdd a weekend shift
Sablewood ClinicMCS-DU-1494 · DuctingLate1.92 MPlant NorthIn production19 Oct12 days lateCapacityAdd a weekend shift
Umber Rail DepotMCS-CH-1309 · ChillersLate1.75 MPlant EastProcurement10 Sep51 days lateMaterial shortExpedite the late part
Marlow Civic CentreMCS-AH-4980 · Air handlingLate1.71 MPlant EastProcurement9 Aug83 days lateMaterial shortExpedite the late part
Kestrel Data HallsMCS-CH-2404 · ChillersLate1.60 MPlant NorthPlanning19 Sep42 days lateDesign changeRelease the new drawing
Oakridge Schools TrustMCS-AH-1941 · Air handlingLate1.57 MPlant NorthIn production26 Aug66 days lateCapacityAdd a weekend shift
Marlow Civic CentreMCS-PU-3824 · Packaged unitsLate1.28 MPlant SouthQuality4 Aug88 days lateMaterial shortExpedite the late part
Pinecrest ResidencesMCS-FC-2604 · Fan coilsLate1.21 MPlant SouthDispatch28 Sep33 days lateWaiting on test slotBook the test bay
Harrowgate Health CampusMCS-PU-4883 · Packaged unitsAt risk1.18 MPlant EastPlanning5 NovDue in 5 daysWaiting on test slotBook the test bay
Umber Rail DepotMCS-AH-1473 · Air handlingLate1.15 MPlant EastDispatch29 Jul94 days lateWaiting on test slotBook the test bay
Westmere LabsMCS-AH-2231 · Air handlingLate1.12 MPlant EastIn production21 Oct10 days lateWaiting on test slotBook the test bay
Valewood TowersMCS-CH-2473 · ChillersAt risk1.10 MPlant EastIn production18 NovDue in 18 daysDesign changeRelease the new drawing
Oakridge Schools TrustMCS-CH-3751 · ChillersAt risk0.96 MPlant NorthIn production12 NovDue in 12 daysMaterial shortExpedite the late part
Cobalt Bay HotelsMCS-DU-4351 · DuctingLate0.76 MPlant NorthPlanning1 Aug91 days lateWaiting on test slotBook the test bay
Tidewater ArenaMCS-DU-2287 · DuctingLate0.76 MPlant NorthDispatch2 Sep59 days lateCapacityAdd a weekend shift
Valewood TowersMCS-PU-1173 · Packaged unitsLate0.70 MPlant EastQuality16 Sep45 days lateQuality holdClear the test result
Alderbank EstatesMCS-FC-4917 · Fan coilsLate0.49 MPlant NorthIn production25 Aug67 days lateQuality holdClear the test result
Alderbank EstatesMCS-CH-4104 · ChillersLate0.32 MPlant SouthDispatch7 Oct24 days lateCapacityAdd a weekend shift
Juniper Logistics ParkMCS-CH-1584 · ChillersAt risk0.30 MPlant NorthPlanning16 NovDue in 16 daysWaiting on test slotBook the test bay
Tidewater ArenaMCS-FC-1916 · Fan coilsAt risk0.27 MPlant NorthQuality18 NovDue in 18 daysQuality holdClear the test result
Oakridge Schools TrustMCS-FC-3308 · Fan coilsLate0.25 MPlant EastProcurement6 Aug86 days lateWaiting on test slotBook the test bay