Plan vs actual
97.0%
On the 97.0% target
Target 97%103.1 of 106.3 M plan made97%
Dashboard · Meridian Climate Systems
Plan against actual, work finished on time and labour efficiency. By plant, line and month, with the orders to rescue first. Data to 31 October 2026.
Rebuilt with made-up data. The real dashboard is internal.
Year to date · All plants
Finished on time and labour efficiency need work. Plant South is furthest behind plan at 90.5%.
97.0%
On the 97.0% target
81.1%
−8.9 pts below the 90.0% target
79.4%
−0.6 pts below the 80.0% target
Tap a plant to filter the page.
Tap a stage to filter the orders below. Hatched work has no stage recorded yet.
| Next action | ||||||
|---|---|---|---|---|---|---|
| Westmere LabsMCS-FC-2322 · Fan coils | Late | Plant SouthIn production | 8 Oct23 days late | Design change | Release the new drawing | |
| Westmere LabsMCS-CH-2939 · Chillers | Late | Plant EastIn production | 5 Oct26 days late | Design change | Release the new drawing | |
| Westmere LabsMCS-AH-2837 · Air handling | Late | Plant SouthIn production | 19 Sep42 days late | Quality hold | Clear the test result | |
| Umber Rail DepotMCS-PU-1828 · Packaged units | Late | Plant NorthIn production | 28 Jul95 days late | Design change | Release the new drawing | |
| Tidewater ArenaMCS-PU-2277 · Packaged units | Late | Plant EastQuality | 16 Sep45 days late | Material short | Expedite the late part | |
| Quayside OfficesMCS-FC-4046 · Fan coils | Late | Plant EastDispatch | 27 Oct4 days late | Design change | Release the new drawing | |
| Sablewood ClinicMCS-PU-4270 · Packaged units | Late | Plant NorthDispatch | 17 Aug75 days late | Waiting on test slot | Book the test bay | |
| Kestrel Data HallsMCS-FC-3267 · Fan coils | Late | Plant SouthIn production | 31 Aug61 days late | Capacity | Add a weekend shift | |
| Sablewood ClinicMCS-DU-1494 · Ducting | Late | Plant NorthIn production | 19 Oct12 days late | Capacity | Add a weekend shift | |
| Umber Rail DepotMCS-CH-1309 · Chillers | Late | Plant EastProcurement | 10 Sep51 days late | Material short | Expedite the late part | |
| Marlow Civic CentreMCS-AH-4980 · Air handling | Late | Plant EastProcurement | 9 Aug83 days late | Material short | Expedite the late part | |
| Kestrel Data HallsMCS-CH-2404 · Chillers | Late | Plant NorthPlanning | 19 Sep42 days late | Design change | Release the new drawing | |
| Oakridge Schools TrustMCS-AH-1941 · Air handling | Late | Plant NorthIn production | 26 Aug66 days late | Capacity | Add a weekend shift | |
| Marlow Civic CentreMCS-PU-3824 · Packaged units | Late | Plant SouthQuality | 4 Aug88 days late | Material short | Expedite the late part | |
| Pinecrest ResidencesMCS-FC-2604 · Fan coils | Late | Plant SouthDispatch | 28 Sep33 days late | Waiting on test slot | Book the test bay | |
| Harrowgate Health CampusMCS-PU-4883 · Packaged units | At risk | Plant EastPlanning | 5 NovDue in 5 days | Waiting on test slot | Book the test bay | |
| Umber Rail DepotMCS-AH-1473 · Air handling | Late | Plant EastDispatch | 29 Jul94 days late | Waiting on test slot | Book the test bay | |
| Westmere LabsMCS-AH-2231 · Air handling | Late | Plant EastIn production | 21 Oct10 days late | Waiting on test slot | Book the test bay | |
| Valewood TowersMCS-CH-2473 · Chillers | At risk | Plant EastIn production | 18 NovDue in 18 days | Design change | Release the new drawing | |
| Oakridge Schools TrustMCS-CH-3751 · Chillers | At risk | Plant NorthIn production | 12 NovDue in 12 days | Material short | Expedite the late part | |
| Cobalt Bay HotelsMCS-DU-4351 · Ducting | Late | Plant NorthPlanning | 1 Aug91 days late | Waiting on test slot | Book the test bay | |
| Tidewater ArenaMCS-DU-2287 · Ducting | Late | Plant NorthDispatch | 2 Sep59 days late | Capacity | Add a weekend shift | |
| Valewood TowersMCS-PU-1173 · Packaged units | Late | Plant EastQuality | 16 Sep45 days late | Quality hold | Clear the test result | |
| Alderbank EstatesMCS-FC-4917 · Fan coils | Late | Plant NorthIn production | 25 Aug67 days late | Quality hold | Clear the test result | |
| Alderbank EstatesMCS-CH-4104 · Chillers | Late | Plant SouthDispatch | 7 Oct24 days late | Capacity | Add a weekend shift | |
| Juniper Logistics ParkMCS-CH-1584 · Chillers | At risk | Plant NorthPlanning | 16 NovDue in 16 days | Waiting on test slot | Book the test bay | |
| Tidewater ArenaMCS-FC-1916 · Fan coils | At risk | Plant NorthQuality | 18 NovDue in 18 days | Quality hold | Clear the test result | |
| Oakridge Schools TrustMCS-FC-3308 · Fan coils | Late | Plant EastProcurement | 6 Aug86 days late | Waiting on test slot | Book the test bay |